|
|
|
|||||||||||||||||||||
|
Irish Independent - 17-01-04 AN Bord Pleanala said it made its decision to sanction
the controversial €100m toxic waste incinerator in The planning board ratified the project by Belgian
firm Indaver by a nine to one vote despite the fact its own inspector,
who chaired an oral hearing into the project last October, recommended
that the plan be rejected. Board inspector Philip Jones recommended that the
project be rejected on seven specific grounds ranging from its residential
impact to its breach of local planning guidelines. The board also admitted that the decision is in
breach of the Cork County Development Plan, which had prompted Cork
Co Council to originally refuse Indaver planning permission last May.
Bord Pleanala said the project was ratified because
of "national policy" which dictates that Indaver said they were delighted by the decision
. "Obviously we're very happy and we feel it is good
for the However, he admitted work on the project was unlikely
to proceed in the short-term. He added: "We must now apply for a licence from
the Environmental Protection Agency (EPA) and, frankly, I would be
surprised if there is not an effort by some opponents to take a judicial
review." The planning board decision follows a three-year
campaign to get the Ringaskiddy project approved. Indaver first unveiled
its plan in 2001. Numerous conditions are attached to the permission
including a stipulation that the incinerator can never handle waste
imported from outside the State. Other conditions include * Indaver make contributions totalling almost €500,000
to Cork Co Council for road, sewerage and environmental works in the
area; * Pay an annual levy to the Council of €127,000;
* Set up a local liaison committee to monitor the
incinerator's operation with two delegates each from the Council (planners),
Council (councillors), local residents and Indaver itself; * Operate the plant strictly within Environmental
Protection Agency and EU guidelines. * Undertake detailed measures to ensure the plant's
impact on the visual and immediate Ringaskiddy environment is minimal.
The planning authority said its decision was taken
in light of the Waste Management Act (1996), the National Hazardous
Waste Management Plan (1992) and the Government's waste policy documents,
Changing our Ways/Delivering Change (1998). "It is considered that, subject to compliance with
the conditions set out, the site is an appropriate location for a
necessary public utility, and that the proposed development would
not seriously injure the amenities of the area (including the Martello
tower, a protected structure)," a planning board statement said. "It would also be acceptable in terms of traffic
safety and convenience, it would not be prejudicial to the future
development of the area for port-related development and would be
in accordance with the proper planning and development of the area."
The statement said it was not unusual to overturn
an inspector's recommendation with 11pc of decisions taken against
such recommendations. An Bord Pleanala discussed the incinerator project
at three separate board meetings before a vote was finally taken this
week. The inspector's report runs to over 360 pages. The board disagreed with the interpretation, and
insisted national priorities must be given precedence over local planning.
Ralph Riegel © Irish Independent |
|||||||||||||||||||||||||||
|
Cork
Harbour Alliance for a Safe Environment |